U.S. General Services Administration

    Administrator's Semiannual 
Management Report to the Congress





Report No. 52
October 1, 2014
to March 31, 2015


U.S. General Services Administration
Denise Turner Roth
Acting Administrator

Office of Administrative Services 
Cynthia A. Metzler
Chief Administrative Services Officer

GAO/IG Audit Response Division 
Leroy Ford
Director

April 2015

This report is in the public domain. Authorization to reproduce it in whole or in part is 
granted. While permission to reprint this publication is not necessary, the citation should be:
U.S. General Services Administration, Office of Administrative Services, GAO/IG Audit 
Response Division, Administrator�s Semiannual Management Report to the Congress, No. 
52, Washington, DC 20405.

To obtain copies of this report,

Write to: U.S. General Services Administration, Office of Administrative Services, GAO/IG 
Audit Response Division, 1800 F Street, NW Washington, DC 20405

E-mail your request to: leroy.ford@gsa.gov 
Call in your request: (202) 501-4786
Obtain a copy of this report on the Agency's Web site at: 
Semiannual Management Report to the Congress


Contents
Synopsis of Audit Activity	4
Overview	5
Organization of Audit Follow-up Program	6
Agency Audit Follow-up Program	6
Agency Audit Follow-up Official	6
The Chief Administrative Services Officer	6
Heads of Services and Staff Offices and Regional Administrators	6
Audits with Disallowed Costs	7
Audits with Better Use Funds	8
Internal Audits	9
Audits under Appeal/Litigation	10
Contract Audits	11
Glossary of Terms	26
Appendix A	28


Synopsis of Audit Activity
In accordance with the Inspector General Act of 1978, as amended, the Administrator is 
required to report directly to the Congress on management decisions and final actions 
taken on audit recommendations made by the Office of Inspector General (OIG) of the 
General Services Administration (GSA). This report covers the semiannual management 
reporting period of October 1, 2014, through March 31, 2015.

The report provides a summary of:

  -	Cases where final action has not been taken on audits one year after the date of the 
management decision.
  -	Implementation of the recommendations by GSA management contained in audit 
reports issued by the OIG.

At the commencement of this semiannual management reporting period, there were audit 
reports with disallowed costs, audits with better use funds, and audits with both 
disallowed cost and better use funds. During the reporting period, a total of 147 audit 
reports  were  pending  final  action  containing  financial  recommendations  totaling
$128,377,912.  There were 143 contract audits with financial recommendations totaling
$1,991,399,347 and seven internal audits with financial recommendations totaling $0.

During the reporting period, management decisions were made on 39 audit reports 
concerning nationwide GSA programs and operations.

Of the 39 audits, 32 of these audits found $18,001,611 in pre-award and post-award 
contract spending which was incorrectly charged to the Government (known as 
disallowed costs). Of the 39 audits, 29 audits recommended that $368,411,539 could be 
used more effectively (known as funds to be put to better use) if management took action 
to implement and complete the OIG recommendations. This information is disclosed in 
Appendix A of this report.

During the six-month period, GSA was able to successfully take final action on a total of 
23 audits. These audits represent the recovery of $1,102,792 in Government funds and 
the identification of $256,896,079 in potential future savings.

As of March 31, 2015, 189 audit reports remained open. There were several audits 
involving claims under appeal or litigation during this reporting period.


Overview
This report, submitted pursuant to the Inspector General Act of 1978, as amended, 
presents management's perspective on audit resolution and follow-up activity at GSA for 
the period beginning October 1, 2014, through March 31, 2015. This is the agency's 
52nd Semiannual Management Report to the Congress since the implementation of the 
Act (Public Law 100-504). The data in the report indicates that GSA's audit follow-up 
efforts continue to play a significant role in the effective management of the agency's 
operations and the accomplishment of its mission which results in better use of 
Taxpayer's dollars.

U.S. General Services Administration Organization
GSA is organized around two major business functions represented by the Federal 
Acquisition Service and the Public Buildings Service. In addition, GSA houses the Office 
of Government-wide Policy, the Office of Citizen Services and Innovative Technologies, 
and a number of Staff Offices that provide support to the other GSA organizations. There 
are 11 regions in the GSA structure.

The Administrator of GSA directs the execution of all GSA functions. Members of the 
Administrator�s office, as well as Regional Administrators and Heads of Services and 
Staff Offices, advise and make recommendations on policy or operational issues of 
national scope. They are also responsible for execution of programs and services within 
their service, region or staff office, under the leadership of the Administrator.


Organization of Audit Follow-Up Program
GSA has effective systems in place for keeping track of audit recommendations. In 
addition, GSA senior management is committed to ensuring that appropriate corrective 
action is taken. Agency managers have the responsibility to act upon the auditor's 
recommendations, with the audit resolution process being supervised by the agency audit 
follow-up official. A description of the responsibilities of GSA officials involved in the audit 
follow-up process is set forth below:

Agency Audit Follow-up Official
The Deputy Administrator is the Agency Audit Follow-up Official responsible for audit 
follow-up activity. As such, this position has overall responsibility for ensuring the 
adequacy of the agency's follow-up system, monitoring the resolution of audit 
recommendations, and ensuring the prompt implementation of corrective actions. The 
Deputy Administrator also makes final decisions to resolve differences between agency 
management and the OIG.
Chief Administrative Services Officer (CASO)
The CASO provides direction and oversight to the officials in the Office of Administrative 
Services (OAS) who manage the GSA's Audit Resolution and Follow-up System. Their 
responsibilities include:

   -	Acting as the liaison with the Government Accountability Office (GAO) for the 
coordination of GAO audits in progress within GSA and for preparation of responses and 
reports for the signature of the Administrator on GAO recommendations as required by 
law;
   -	Ensuring timely resolution and implementation of internal and external audit 
recommendations made by the GAO and the OIG;
   -	Overseeing the collection and proper accounting of monetary amounts determined 
due to the Government as the result of audit-related claims;
   -	Analyzing GSA's programs, upon request from the Administrator, particularly as 
related to past or present audit recommendations; and,
   -	Maintaining an automated report control system for both internal and external 
audits that provides an accurate means for tracking and documenting actions taken in 
implementing audit recommendations.

Heads of Services and Staff Offices and Regional Administrators
Heads of Services and Staff Offices and Regional Administrators, to whom audit 
recommendations pertain, have primary responsibility for resolving and implementing 
recommendations promptly. Their responsibilities include:

   -	Ensuring controls are implemented to provide timely, accurate, and complete 
responses to audit reports;
   -	Developing,	advocating,	and	documenting	agency	positions	on	audit 
recommendations;
   -	Preparing responses for GAO draft reports and transmittals for final GAO reports 
in coordination with OAS;
   -	Providing comments on audit decision papers prepared by the OIG to ensure that 
management's position on unresolved audit recommendations is properly stated.




Final action for the six-month period 
Ending MARCH 31, 2015

A. Audit reports for which final action had 
not been taken by the commencement of 
the reporting period.

B. Audit reports on which GSA/OIG 
management decisions were made during 
the reporting period.
Number of Audit 
Reports

147



32
Disallowed 
Costs

$128,377,912



$18,001,611
C. Audit reports on which final action was 
taken during the reporting period.
(i)	the dollar value of disallowed costs
-	collections.................	$1,102,792
-	offset ...................	$1,145
-	property in lieu of	$0
cash...
-	surplus ...............	$8,155
-	other ...............	$0
(ii) the dollar value of disallowed costs 
that were written off by management.
23
$1,109,802


$1,109,802





$0
D. Audit reports for which no final action 
has been taken by the end of the reporting 
period.
189
$135,877,518



Final action for the six-month period	Number of 
Ending MARCH 31, 2015		Reports
A. Audit reports for which final action	143
had not been taken by the 
commencement of the reporting period.
B. Audit reports on which	29
management decisions were 
made during the reporting period.
Audit
 No budget Impact 
(Actual and Estimated)

$1,991,399,347



$368,411,539
Budget 
Impact

$0



$0
C. Audit reports on which final 
action was taken during the
19
$256,896,079
$0
reporting period.



(i) the actual dollar value of

$33,438
$0
recommendations that were



actually completed.



(ii) the actual dollar value of

$3,027
$0
recommendations that



management has subsequently



concluded should not or could not



be implemented or completed.



(iii) the actual dollar value of

$0
$0
recommendations that



management has subsequently



concluded should not or could not



be determined (calculated).



(iv) the estimated dollar value of

$256,865,668
$0
''funds to be put to better use'' as



agreed to by GSA management



and the OIG.



D. Audit reports for which no final
action has been taken by the end of 
the reporting period.
168
$2,030,538,172
$0


Internal Audits
Audits with Management Decisions made prior to March 31, 2014, but 
with Final Action not taken as of March 31, 2015



REPORT NUMBER 
TITLE OF REPORT


DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS


REASON FOR NO 
FINAL ACTION

PROJECTED 
COMPLETION 
DATE


Disallowed 
Costs
Better Use 
Funds


A090172PRR11013
Recovery Act Report - 
GT "Mickey" Leland 
Federal Building 
Renovation Project: 
Construction Contract 
Audit of PBS's Major 
Construction and 
Modernization 
Projects Funded by 
The American 
Recovery and 
Reinvestment Act of 
2009






08/19/2011






$0






$0





Audit is in the 
implementation 
stage.






05/29/2015
A110100Q9P12009
Audit of Management 
Controls Within the 
Network Services 
Division Pacific Rim 
Region, Federal
Acquisition Service



05/30/2012



$0



$0


Audit is in the 
implementation 
stage.



05/29/2015

A120001PFR13007
Audit of GSA's 
Controls over the 
National Capital 
Region's 
Reimbursable Work 
Authorizations



09/11/2013



$0



$0


Audit is in the 
implementation 
stage.



10/30/2015


Audits under Appeal/Litigation



   REPORT NUMBER 
NAME OF CONTRACTOR

DATE OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS


Disallowed 
Costs
Better Use 
Funds
A100213P9X11023

Cobb Mechanical Contractors, 
Colorado Springs, CO

01/27/2011

$0

$4,864,953
A110070P9X11058

Bergelectric Corporation

06/01/2011

$0

$2,828,737
A100170P9X11077

Caddell Construction Company, 
Incorporated

07/27/2011

$0

$5,948,364
A110021P9X11093

Myrex Industries

09/08/2011

$0

$5,773,586
A120065P9X12019

Bergelectric Corporation

02/03/2012

$0

$322,910
A120070P9X12029

Cobb Mechanical Contractors

03/28/2012

$0

$194,480
A120069P9X12039

Cleveland Construction, Inc.

05/09/2012

$0

$1,207,623
A120063P9X12055

Caddell Construction Co., Inc.

08/09/2012

$0

$7,975,645
A130034P4X13032

Caddell Construction Co., Inc

03/28/2013

$0

$5,001,544
A130093P4X14045

Amthor Steel, Inc.

06/26/2014

$0

$2,065,356






REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A100193Q4X11014
The Stratix Corporation



11/24/2010



$41,168



$0
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A100213P9X11023
Cobb Mechanical 
Contractors, Colorado 
Springs, CO




01/27/2011




$0




$4,864,953
Litigation in 
Process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process

A100075Q7X11022
Cort Business Services 
Corporation


01/27/2011


$0


$1,575,000
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A100114Q2X11036
Ahura Scientific, Inc.



03/29/2011



$123,252



$0
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor

A100171P9X11025
Layton Construction 
Company, Inc.


02/02/2011


$0


$1,899,985
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A110063QAX11053
IntelliDyne, LLC


05/16/2011


$3,948,160


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds




A110070P9X11058
Bergelectric Corporation




06/01/2011




$0




$2,828,737
Litigation in 
Process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process

A110108Q4X11063
Protective Products 
Enterprises


06/13/2011


$0


$553,510
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A110132PRX11067
R.A. Heintges & Associates


07/08/2011


$0


$95,839
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A110132PRX11068
Smith-Miller & Hawkinson 
Architects, LLP


07/08/2011


$0


$6,225,926
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor
A110140PAX11071
Architect/Engineering 
Proposal Lehman Smith 
McLeish, PLLC, 
Subcontractor to Smith- 
Miller & Hawkinson 
Architects LLP



07/14/2011



$0



$176,478
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor



A090112Q6X11060
ITS Services, Inc




06/07/2011




$21,927,177




$0

In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A100140Q5X11070
Veterans Imaging Products, 
Inc.


07/07/2011


$3,893


$496,000
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A110088Q3X11079
Global Protection USA, Inc


07/28/2011


$29,337


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor



A100170P9X11077
 Caddell Construction 
Company, Incorporated




07/27/2011




$0




$5,948,364
Litigation in 
Process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process


A100119Q6X11081
Noble Sales Co., Inc.


08/03/2011


$0


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor
A110133PAX11080
Architect Engineer 
Proposal Arup USA, Inc., 
Subcontractor to Smith- 
Miller & Hawkinson 
Architects LLP


08/04/2011


$0


$134,505
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A110180P9X11084
RTKL Associates, Inc.


08/15/2011


$0


$412,057
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A110136Q3X11088
Konica Minolta Business 
Solutions U.S.A., Inc.



08/25/2011



$11,599



$35,625,685
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor



A110021P9X11093
Myrex Industries




09/08/2011




$0




$5,773,586
Litigation in 
Process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process


A110067Q2X11092
Clifton Gunderson, LLP


09/09/2011


$1,374


$1,196,561
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A110174Q4X11097
Protective Products 
Enterprises


09/15/2011


$63,992


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A110146P9X11095
White Construction 
Company


09/12/2011


$0


$829,494
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A100210Q5X12001
Labat-Anderson, Inc.


10/13/2011


$0


$3,200,000
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A110176Q4X12010
Fontaine Trailer Company, 
Incorporated


12/07/2011


$0


$4,648,519
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A090106Q3X09084
Perot Systems Government 
Services, Inc.



08/19/2009



$34,758



$33,743,210
In the Process of 
Collection - GSA is 
in the process of 
collecting funds 
owed the 
government from 
the contractor


A110178Q3X12014
Sharp Electronics 
Corporation




12/22/2011




$49,653




$6,752,403

Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor

A110191QAX12016
Paradigm Technologies, 
Inc.


12/27/2011


$0


$2,557,773
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A110186Q7X12018 
BRSI, L.P.


01/23/2012


$0


$7,425,000
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor



A120065P9X12019
Bergelectric Corporation




02/03/2012




$0




$322,910
Litigation in 
Process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A120075P4X12020
Enola Contracting Services, 
Inc.


02/08/2012


$0


$121,312
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A110089Q2X12021
Quality Software Services, 
Inc.


02/22/2012


$714


$17,652,348
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A120021Q3X12023
Presidio Networked 
Solutions, Inc.


03/02/2012


$31,878


$2,427,935
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120074Q5X12028
Kimball International, Inc.


03/27/2012


$0


$29,500,000
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor



A120070P9X12029
Cobb Mechanical 
Contractors




03/28/2012




$0




$194,480
Litigation in 
Process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process


A120090Q3X12032
Mine Safety Appliances 
Company



04/10/2012



$1,511



$3,270,118
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A110143Q5X12034
The J. Diamond Group, Inc.


04/12/2012


$8,555


$21,200,000
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120069P9X12039
Cleveland Construction, 
Inc.




05/09/2012




$0




$1,207,623
Litigation in 
Process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process


A110169Q3X12048
Oce North America, Inc.


06/29/2012


$225,180


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A120126Q5X12050
Hamilton Products Group, 
Inc.


07/06/2012


$0


$15,000,000
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120136P4X12053
Lenex Steel Company


07/17/2012


$0


$834,067
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor



A120063P9X12055
Caddell Construction Co., 
Inc.




08/09/2012




$0




$7,975,645
Litigation in 
Process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A110209Q6X12057
Propper International 
Sales, Inc.


08/15/2012


$2,063,375


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120083P9X12059
M.A. Mortenson Company


08/21/2012


$0


$2,814,148
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A120061Q5X12060
Schneider Electric USA, 
Inc.


08/23/2012


$110,209


$15,000,000
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A120121P9X12064
Alutiiq International 
Solutions, LLC


09/18/2012


$0


$1,692,286
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A090232PCX09101
Haley & Aldrich, Inc.



09/09/2009



$0



$11,762
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A090234PCX09102
HDR Architecture, Inc.



09/10/2009



$0



$809,387
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A120141P9X12065
Turner Construction 
Company


09/20/2012


$0


$858,840
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120148P9X13003
Siemens Industries, Inc.


10/17/2012


$0


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A090202Q6X10016
Computech, Inc.


11/09/2009


$0


$19,043,879
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A090159Q5X10022
RCF Information Systems, 
Inc.


12/10/2009


$4,459


$522,882
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A090140Q6X10081
Systems Research and 
Applications Corporation


08/24/2010


$392,685


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A100148P9X10087
Alutiiq International 
Solutions, LLC


09/16/2010


$0


$4,096,596
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A090133Q7X11005
SeaArk Marine, Inc.



10/27/2010



$1,130,227



$0
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A120066Q5X13004
Life Fitness, Inc.



11/02/2012



$0



$29,300,000
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A120071Q2X13002
ICF Z-Tech, Inc.


10/16/2012


$14,580


$166,639
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120155Q3X13007
Avion Solutions, Inc.


11/21/2012


$0


$4,523,340
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor



A110147Q6X13010
Xerox Corporation




12/06/2012




$0




$8,511,087

In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120165P4X13019
Skanska USA Building, Inc.


01/30/2013


$0


$82,475
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120098Q2X13025
Dynamics Research 
Corporation



03/01/2013



$8,973



$6,040,027
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A120147Q2X13028
Harris Corporation, RF 
Communications Division


03/20/2013


$44,256


$53,543,014
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120178Q3X13026
VT Aepco, Inc.



03/05/2013



$76,352



$38,059,421
Unresolved - 
Agreement has not 
been reached 
between OIG and 
Contracting Officer 
on the Decision 
Record


A120109Q7X13030
ICF Macro, Inc.


03/21/2013


$0


$11,456,930
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A120095Q7X13024
Military Personnel Services 
Corporation


02/28/2013


$87,379


$16,083,715
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A120127Q4X13033
General Dynamics 
Information Technology, 
Inc.


03/29/2013


$147,371


$48,528,780
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A120142QAX13031
Science Applications 
International Corporation 
(SAIC)


03/28/2013


$97,020


$280,483,385
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A130034P4X13032
Caddell Construction Co., 
Inc




03/28/2013




$0




$5,001,544
Litigation in 
Process - The 
contractor has 
appealed the 
Contracting 
Officer's decision 
and the audit is 
now in the litigation 
process


A130047P4X13040
Skanska USA Building, Inc.


05/13/2013


$0


$1,189,218
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A130044Q6X13044
Tektronix, Inc.


05/29/2013


$0


$6,200,000
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A110160Q7X13042
i2, Incorporated


05/28/2013


$2,064,798


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120113Q2X13046
MSC Industrial Direct Co.


06/03/2013


$2,278


$55,064,975
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120175Q3X13041 
STG Inc.


05/22/2013


$0


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds


A130069Q7X13051
L-3 Communications Vertex 
Aerospace, LLC


06/28/2013


$248,423


$24,112,597
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A120152Q6X13054
Herman Miller, Inc.


07/11/2013


$175,056


$20,574,360
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A120134Q6X13059
International Business 
Machines Corporation


07/31/2013


$0


$482,854,052
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor

A120156Q4X13065
General Dynamics 
Information Technology, 
Inc.



09/09/2013



$60,328



$49,343,348
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A130077Q4X14004
Intuitive Research and 
Technology Corporation



10/29/2013



$162



$34,503,942
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A130087Q3X14002
Accenture Federal Services 
LLC



10/24/2013



$0



$10,772,764
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A120087Q9X13067
Eaton Corporation



09/30/2013



$0



$20,041,706
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A130086Q3X14001
Sea Box, Inc.



10/24/2013



$3,032



$0
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A130079Q5X14008
Allsteel Inc.



12/12/2013



$0



$5,900,000
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A130073Q4X14010
Torch Technologies, Inc.



12/20/2013



$34,379



$22,243,159
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A130088Q2X14013
Provengo LLC


12/20/2013


$0


$0
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A130080QAX14015
Intelsat General 
Corporation



01/24/2014



$0



$35,211,852
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor




REPORT NUMBER 
NAME OF 
CONTRACTOR

DATE 
OF 
REPORT
MANAGEMENT DECISION 
AMOUNTS

REASON FOR 
NO
FINAL ACTION


Disallowed 
Costs
Better Use 
Funds



A120143Q2X14016
Centra Technology, Inc.



01/27/2014



$0



$4,508,222
Price/Settlement 
Negotiated - 
Negotiations have 
been completed 
between 
Contracting Officer 
and contractor


A100210Q5X13064
Labat-Anderson, Inc.


09/04/2013


$0


$517,335
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


A130085Q3X13063
Bart & Associates, Inc.


09/06/2013


$130,030


$48,373,190
In Negotiation - 
Negotiations are 
proceeding 
between 
Contracting Officer 
and contractor


Glossary of Terms

The following definitions, based on the Inspector General Act Amendments of 
1988, apply to terms used in this Semiannual Management Report:

Questioned Costs. Costs questioned by the OIG as a result of:

 �	an alleged violation of a provision of a law, regulation, contract, grant, 
cooperative agreement, or other agreement or document governing the 
expenditure of funds;

 �	a finding that, at the time of an audit, such cost is not supported by adequate 
documentation;

 �	a finding that the expenditure of funds for the intended purpose is unnecessary 
or unreasonable.

Disallowed Cost. Questioned costs that GSA management in a management 
decision sustained or agreed should not be charged to the Government.

Recommendation that Funds be Put to Better Use. A recommendation by the 
OIG that funds could be used more efficiently if management took action to 
implement and complete the recommendations, including:

�	reductions in outlays;

�	de-obligation of funds from programs or operations;

 �	withdrawal of interest subsidy costs on loans or loan guarantees, insurance or 
bonds;

 �	costs not incurred by implementing recommended improvements related to the 
operations of the establishment, a contractor or grantee;

 �	avoidance of unnecessary expenditures noted in pre-award reviews of contract 
or grant agreements;

�	any other savings that are identified specifically.

Management Decision. The evaluation by management of the findings and 
recommendations included in an audit report and the issuance of a final decision 
by management and concurrence by the OIG concerning its response to such 
findings and recommendations, including planned corrective actions to remedy 
weaknesses identified in the report.


Final Action. The completion of all actions that GSA management concluded in its 
management decision were necessary with respect to the findings and 
recommendations included in the audit report. In the event that GSA management 
concluded no action was necessary, final action occurred when the management 
decision was made.

Management Actions - Questioned Costs. The following is a list of the different 
management actions used by GSA management to resolve questioned costs in an 
audit report.

 �	Audit reports on which management decisions were made during the 
period: Data pertaining to the number of audit reports on which management 
decisions were made during the period and the associated amount of disallowed 
costs was furnished by the OIG.

 �	Write-offs: For the purposes of this report, write-offs are interpreted to 
represent the difference between the disallowed cost and the amount successfully 
recovered.

Management Actions - Better Use Funds. The following is a list of the different 
management actions used by GSA management to resolve the "better use" of 
funds in an audit report.

 �	Better Use Funds: The figure represents amounts cited as "cost 
avoidance" and "funds to be put to better use," as agreed to by GSA management 
and the OIG. Prior to April 1990, no funds were identified by the OIG specifically 
as "funds to be put to better use," and no management decisions were issued 
based on the consideration of "better use" of funds.

 �	Budget Impact Funds: Funds identified as "budget impact" involve the 
obligation process. Audit-related savings of these funds, depending on the 
particular fund involved, may be available for reprogramming.

 �	No Budget Impact Funds: Funds identified as "no budget impact" are 
composed of estimated and actual amounts, and do not involve obligated monies, 
and, therefore, cannot be construed as having a material effect on GSA''s 
appropriated funds.

 �	Audit reports on which management decisions were made during the 
period: Data pertaining to the number of audit reports on which management 
decisions were made during the period and the associated dollar amounts agreed 
to by management were furnished by the OIG.

 �	Value of recommendations that management concluded should not or 
could not be calculable: Management was unable to determine the award 
amounts and "better use funds" implemented since the amount is included in the 
overall award to the prime contractor and savings could not be determined.


Appendix A







This page is left blank intentionally.


 




U.S. General Services Administration
1800 F Street, NW 
Washington, DC 20405

www.gsa.gov